Round the clock power supply for Mahakumbh 2025 is sorted

Prayagraj: The power system will be fully functional and efficient in Maha Kumbh 2025. There will be no shortage of electricity anywhere in the entire fair area, for this the fair administration has made extensive preparations in coordination with the electricity department.

Under this, two new sub-stations are being constructed. At the same time, the work of increasing the capacity of sub-stations, construction of interlink line is also in progress. Not only this, the process of making the power line underground is also going on. Along with this, many other important works are also being carried forward rapidly.

Construction of two new sub-stations

In view of Maha Kumbh 2025, 132/33 kV transmission sub-station Hetapatti is being constructed in Gangapar Jhunsi area. This sub-station will ensure uninterrupted power supply to the fair area and urban and rural areas (Awas Vikas, Trivenipuram, Sahason, Hetapatti) with a population of about 2.50 lakh. Similarly, New Bailey substation is also being built, which will provide electricity to about 1 lakh population of areas like Bailey, Myorabad, Katra and Rajapur.

Capacity enhancement of substations

The capacity of Phaphamau substation is being increased, which will provide better power supply to about 50 thousand residents of Phaphamau market, rural area and Shantipuram. Along with this, the major substations of the city are being connected through interlink line, which will provide uninterrupted power to 7 lakh people.

Construction of interlink line

12 interlink lines are being built to connect 12 major 33/11 kV substations of the city. This will supply electricity to areas like Civil Lines, Bairhana, Rambagh, High Court, Karaili, Khusrobagh, Prayagraj Junction, Bailey and Phaphamau.

Process of undergrounding the power line

All HT and LT lines of Airport Road, Baghambari Road and Peshvai Marg have been undergrounded. This will enhance the beauty of these areas and prevent accidents. Also, the obstructing power lines during the procession of the Akharas have been removed and buried underground.

Installation of RMU

To keep the power supply running continuously during Maha Kumbh, 33 KV RMUs (Ring Main Unit) are being installed at Awas Vikas, Daraganj, Fort Road and Someshwarnath sub-centres. In case of any fault, the supply will be restored within 10 to 15 seconds, which will provide uninterrupted power supply to the fair area.

Electricity system of parking and parade area

33 KV lines of the parking area and parade area have been buried underground, which will prevent any power-related accident during the fair. Designer poles are being installed in the parade area, which will ensure lighting along with beauty in the area.

Undergrounding of obstructing lines at railway stations and RUBs

The power lines in front of Prayagraj Junction and Prayag Station have also been undergrounded. This will not cause any obstruction to the movement of devotees during the fair and a safe route can be maintained in front of the railway stations.

---------------------------------------------------------------------- -----------------------------------------------------------