Lucknow: The construction of the Ramjanmabhoomi complex in Ayodhya has gained significant momentum, especially as the number of visitors to Ramlala has returned to pre-pandemic levels. Despite the continuous influx of devotees, work on the project has remained largely unaffected. While the high footfall has occasionally caused minor slowdowns, construction activities have proceeded uninterrupted.
Completion of Saptarishi Temples and Ongoing Developments
Several major structures within the complex have already been completed. Notably, all seven Saptarishi temples are now fully constructed. Additionally, the two temples dedicated to various deities at the center of the rampart have had their summits completed. The Yatri Suvidha Kendra also houses the Goswami Tulsidas temple, where idol installation is set to commence this month under the supervision of the Shri Ram Janmabhoomi Teerth Kshetra Trust.
Ram Mandir’s Core Structure Nearing Completion
Construction efforts remain focused on several key areas within the Ramjanmabhoomi complex. These include the main peak of the Ram temple, its first and second floors, an 800-meter-long rampart, seven Saptarishi temples, and six temples dedicated to gods and goddesses. The temple building committee continues to review progress on a monthly basis, ensuring that the work proceeds smoothly despite necessary adjustments to timelines.
Challenges and Steady Progress Amid Devotee Influx
The recent Maha Kumbh in Prayagraj temporarily impacted construction efforts as large crowds in Ayodhya affected the transport of workers and building materials. However, a well-maintained stockpile of stones ensured that work remained on schedule. Thanks to the meticulous planning of Larsen & Toubro, the primary construction agency, the first level of the Ram Mandir, the sub-temples within the rampart, and all seven Saptarishi temples have been completed.
Currently, four additional temple spires dedicated to gods and goddesses are under construction, with completion expected soon. Meanwhile, efforts continue on the temple’s rampart and second floor. The rampart still requires approximately 2.50 lakh cubic feet of stone, while the second level is steadily nearing completion. As of now, 5.70 lakh cubic feet of pink sandstone has been utilized in the temple’s main spire, which has already reached 21 layers. With eight layers still pending, this segment of construction is expected to be completed within the next two months.
Delays in Sheshavtar Laxman Ji’s Temple
While most aspects of the Ramjanmabhoomi complex are progressing rapidly, the construction of Sheshavtar Laxman Ji’s temple, situated southwest of the Ram Mandir, has encountered delays. Of the required 16,000 cubic feet of stone, only 6,000 cubic feet have been utilized so far. Design modifications contributed to these delays, as the temple building committee revised the structure twice before finalizing the plans.
Despite occasional challenges, Project Director Vinod Kumar Mehta of L&T remains optimistic, affirming that all construction work is proceeding at a swift pace. With the trust and committee ensuring efficient oversight, the completion of the Ramjanmabhoomi complex remains on track, reinforcing Ayodhya’s position as a major spiritual and cultural hub.